In 2014 we collaborated with Riko to install four cranes into the high-bay warehouse of a creamery in Brest. The cranes are 24,7 m high and have a load capacity of 1000 kg. In 2021-2022 we elongated the corridors and added one more crane in each of them, so each corridor now has two operational cranes. We added a special lower crane to serve the area where final palettes are commissioned.

Customer: Creamery Savuškin, Brest, Belarus

Partner: RIKO d.o.o.

Field of work: Logistic systems

Year: 2014, 2021 expansion with 4 more cranes and a special crane for goods commissioning

Scope:
4 + 4  storage-retrieval machines 24,7 m high  pallets:

  • design,
  • manufacturing,
  • overseeing the assembly,
  • Software for PLC
  • commissioning