INSTALLED HYDROMECHANICAL EQUIPMENT:

Radial gates with flaps – 5 sets
Spilway width: 15.000 mm
Height of radial gate: 8070 mm
Weight of radial gate: 68.100 kg
Width of flap gate: 12.300 mm
Height of flap gate: 3.300 mm
Weight of flap gate: 13.375 kg

Service gates – 5 sets
Width of service gates: 15.000 mm
Height of service gates: 14.270 mm
Weight of service gates: 73.920 kg

Floating downstream service gates – 1 set
Width of service gates: 15.000 mm
Height of service gates 8.250 mm
Weight of service gates: 53.540 kg

Intake trash racks – 3 sets with embedded parts
Width of racks: 15.400 mm
Height of racks: 12.700 mm
Weight of racks: 159.820 kg

Intake wheel gates – 1 set of gates with 3 sets of embedded parts
Width of intake gates: 15.400 mm
Height of intake gates: 12.700 mm
Weight of intake gates: 151.035 kg

Outlet gates – 3 sets with embedded parts and lifting mechanism
Width of outlet gates: 15.400 mm
Height of outlet gates: 5.800 mm
Weight of outlet gates: 64.200 kg
HPP Brežice is the fifth hydroelectric power plant in the chain of six HPPs on the lower Sava with a nominal capacity of 47.4 MW. It is of the flow-accumulation type with three vertical aggregates installed with a nominal flow of 500 m3/s, five flow fields and an average annual production of 161 GWh.
You can read more about the project here.
Investor: HESS, Hidroelektrarne na spodnji Savi d.o.o.
Main Contractor: Riko d.o.o.
Subcontractor: Iskra Impuls d.o.o.
Supervisor: HSE Invest d.o.o.
Field of work: Hydromechanical equipment
Year of production: 2017
Scope of performed works: Erection of hydromechanical equipment